NE-4's Rajasthan section is the longest in any state: 373 km, from Munpur Karmala village in Alwar district to Moondiya village in Kota district. It's also where the Delhi–Mumbai Expressway first opened, where it goes under a tiger reserve, and, since August, where it's most closely watched by cameras.
This guide is organised around where you're going. For the alignment itself, see our route page.
How it opened
| Date | What opened | |---|---| | 12 Feb 2023 | Sohna–Dausa–Lalsot, 246 km, inaugurated by the Prime Minister | | Oct 2023 | Dausa–Sawai Madhopur | | Dec 2024 | Kota–Laban, 80 km | | 27 Jul 2026 | Mukundra tunnel, Delhi-bound tube only |
Before Kota–Laban opened, drivers coming up from Madhya Pradesh had to leave at Modak and take the old road through Kota, Tonk and Lalsot, rejoining at Lalsot, as DNA India described when the MP section opened in 2023.
After December 2024, the one remaining break in Rajasthan was around the Mukundra tunnel near Kota, where traffic used a diversion through the Dara valley. Northbound traffic has gone through the tunnel since July 2026. Southbound traffic still takes the diversion.
Exits by destination
| Going to | Leave at | |---|---| | Alwar | SH-14 interchange at Seetal village, near Baroda Meo | | Rajgarh, Mandawar | NH-921 interchange at Pinan | | Jaipur | Bandikui, for the 67 km NE-4C spur to Bagrana on Jaipur's ring road; or the NH-21 Dausa interchange at Bhandarej | | Lalsot | NH-148 at Dungarpur, or NH-23 at Chimanpura | | Sawai Madhopur, Ranthambore | NH-552 interchange at Jaisapura | | Bundi | SH-29 interchange east of Indragarh | | Kota | NH-27 interchange at Karariya, or NH-52 at Mandana | | Rawatbhata | SH-9A interchange at Chechat |
Our Delhi to Jaipur guide compares the two Jaipur routes. Between Sawai Madhopur and Kota, the alignment passes east of Bonli and Lakheri, away from the towns themselves.
Tolls
Rajasthan has more NE-4 plazas than any other state: 21 of the 38 in the NHAI register we use. They include Sheetal, Pinan, Bhandaraj, Dungarpur, Bonli, Laban, Karadiya and Chechat, most of them named after the interchange villages above, plus Bagrana at the Jaipur end of the spur. All are FASTag-only. NHAI hasn't published per-plaza rates for most of them; our toll rates page explains how NE-4 charges by distance.
What changed in 2026
The Mukundra tunnel opened, one way. The 4.9 km tunnel under the Mukundra Hills Tiger Reserve near Chechat took its first Delhi-bound traffic on 27 July. We haven't found a report that the second tube has opened, and fuel, gas and hazardous-chemical carriers are barred. Details in our Mukundra tunnel guide.
Cameras arrived on Kota–Bundi. NHAI put 650 AI cameras on the 133 km between Kota and Bundi, ETV Bharat reported in August, with challans for speeding, average speed, stopping, lane discipline and wrong-side driving from September. The limits are 120 km/h for cars, 100 for buses and 80 for trucks. See how the challans work.
Road quality was in the news too. Drivers reported long humps in the Kota–Jaipur stretch's pavement in August, and parts of the Dausa and Sawai Madhopur stretches had surface failures that featured in NHAI's disciplinary action. We covered both in our pavement report and quality issues story.
On 17 October, eight people died near Kota when a tempo traveller left the expressway at dawn after an overnight drive. A passenger said the driver must have dozed off. Our fatigue guide looks at what that means for planning a long trip.
Coming next around Kota
At Mandana on 8 July, Nitin Gadkari announced two Kota projects, Business Today reported: a 21 km four-lane spur linking Kota to the expressway, approved at ₹1,000 crore, and a 10 km four-lane Mukundara bypass on NH-52 towards Jhalawar at ₹551 crore. He said work on both would start within three months. We haven't seen reports that it has.
Driving notes
The four tiger reserves along this section are Sariska, Ranthambore, Mukundra Hills and Ramgarh Vishdhari, and NE-4 has five wildlife crossings between them. Our wildlife crossings post covers how they work.
It's a long section with long gaps between towns, so plan fuel and breaks before you need them.
Heading south past Kota, allow time for the tunnel diversion.
Sources: our route data and the expressway's Wikipedia entry (alignment, interchanges, opening dates); DNA India, Sep 2023; Ommcom News (IANS), 27 Jul 2026; ETV Bharat, 6 Aug 2026 (Hindi); PTI via ThePrint, 17 Oct 2026; Business Today, 9 Jul 2026; NHAI NH fee plaza register (our toll plaza data).